In which of the following ADM Phases do building blocks become implementation-specific?
The correct answer is E. Phase E. Building blocks become implementation-specific during Phase E (Implementation Governance) of the Architecture Development Method (ADM). This phase focuses on overseeing the implementation of the architecture.
Question
In which of the following ADM Phases do building blocks become implementation-specific?
Options
- APhase A
- BPhase B
- CPhase C
- DPhase D
- EPhase E
How the community answered
(50 responses)- A8% (4)
- B4% (2)
- C2% (1)
- E86% (43)
Why each option
Building blocks become implementation-specific during Phase E (Implementation Governance) of the Architecture Development Method (ADM). This phase focuses on overseeing the implementation of the architecture.
Phase A, Architecture Vision, defines the high-level vision and scope, not implementation specifics.
Phase B, Business Architecture, defines the organizational structure and business processes, not implementation details.
Phase C, Information Systems Architectures (Data and Application), defines logical system components, not their specific implementation in projects.
Phase D, Technology Architecture, defines logical and physical technology components but is still prior to the hands-on governance of project implementation.
Phase E, Implementation Governance, is where the architecture definition is translated into actual implementation projects, and building blocks are specified in terms of solution architectures and specific components.
Concept tested: TOGAF ADM Phase E characteristics
Source: https://www.opengroup.org/togaf/documentation/togaf-standard-10th-edition/implementation-governance-phase-e