Complete the sentence. In the Preliminary Phase, all of the following are part of preparing the organization to undertake successful enterprise architecture, except __________.

The correct answer is E. identifying stakeholders and their concerns. In the TOGAF Preliminary Phase, identifying stakeholders and their concerns is not explicitly part of preparing the organization for enterprise architecture, as this is typically handled in later phases.

ADM Prelim Phase

Question

Complete the sentence. In the Preliminary Phase, all of the following are part of preparing the organization to undertake successful enterprise architecture, except __________.

Options

  • Adefining architecture principles
  • Bdefining relationships between management frameworks
  • Cdefining the enterprise
  • Devaluating the enterprise architecture maturity
  • Eidentifying stakeholders and their concerns

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    2% (1)
  • E
    91% (42)

Why each option

In the TOGAF Preliminary Phase, identifying stakeholders and their concerns is not explicitly part of preparing the organization for enterprise architecture, as this is typically handled in later phases.

Adefining architecture principles

Defining architecture principles is a key activity in the Preliminary Phase, as these principles guide all subsequent architecture work.

Bdefining relationships between management frameworks

Defining relationships between management frameworks is part of establishing the architectural governance and integrating it within the enterprise's existing frameworks in the Preliminary Phase.

Cdefining the enterprise

Defining the enterprise, including its organizational structure and scope for architecture, is a foundational activity in the Preliminary Phase.

Devaluating the enterprise architecture maturity

Evaluating the enterprise architecture maturity helps to tailor the architecture approach and plan for improvement, which is part of the Preliminary Phase.

Eidentifying stakeholders and their concernsCorrect

While stakeholders are crucial, identifying specific stakeholders and their detailed concerns is primarily a task performed in Phase A (Architecture Vision) and subsequent phases of the ADM, where a more detailed scope and engagement plan are established. The Preliminary Phase focuses on establishing the architecture capability itself.

Concept tested: TOGAF Preliminary Phase activities

Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap05.html