OG0-093 · Question #311
In which Phase of the TOGAF ADM is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?
The correct answer is A. Phase F. Phase F of the TOGAF Architecture Development Method (ADM) focuses on creating a detailed Implementation and Migration Plan, often collaborating with portfolio and project managers.
Question
In which Phase of the TOGAF ADM is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?
Options
- APhase F
- BPhase D
- CPhase G
- DPhase E
- EPhase A
How the community answered
(26 responses)- A88% (23)
- C4% (1)
- D8% (2)
Why each option
Phase F of the TOGAF Architecture Development Method (ADM) focuses on creating a detailed Implementation and Migration Plan, often collaborating with portfolio and project managers.
Phase F, known as Migration Planning, specifically addresses the need to formulate a comprehensive implementation and migration strategy. This includes identifying migration projects and creating a detailed plan that aligns with the enterprise's needs and involves portfolio and project management for execution oversight.
Phase D (Technology Architecture) focuses on developing the technology architecture, not implementation and migration plans.
Phase G (Implementation Governance) focuses on overseeing the implementation, not creating the initial plan.
Phase E (Opportunities and Solutions) focuses on identifying delivery vehicles for the architecture, not the detailed migration plan.
Phase A (Architecture Vision) focuses on establishing the architecture vision and scope, which precedes detailed planning.
Concept tested: TOGAF ADM Phase F - Migration Planning
Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap05.html#tag_05_06