What level of risk is the risk categorization prior to determining and implementing mitigating actions?
The correct answer is E. Initial. https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html
ADM Guidelines and Techniques
Question
What level of risk is the risk categorization prior to determining and implementing mitigating actions?
Options
- ACritical
- BResidual
- CLow
- DMarginal
- EInitial
How the community answered
(32 responses)- B6% (2)
- C3% (1)
- D3% (1)
- E88% (28)
Explanation
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html
Topics
#risk management#initial risk#risk categorization