What level of risk is the risk categorization prior to determining and implementing mitigating actions?

The correct answer is E. Initial. https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html

ADM Guidelines and Techniques

Question

What level of risk is the risk categorization prior to determining and implementing mitigating actions?

Options

  • ACritical
  • BResidual
  • CLow
  • DMarginal
  • EInitial

How the community answered

(32 responses)
  • B
    6% (2)
  • C
    3% (1)
  • D
    3% (1)
  • E
    88% (28)

Explanation

https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html