OG0-093 · Question #303
OG0-093 Question #303: Real Exam Question with Answer & Explanation
The correct answer is E: Initial. https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html
Question
What level of risk is the risk categorization prior to determining and implementing mitigating actions?
Options
- ACritical
- BResidual
- CLow
- DMarginal
- EInitial
Explanation
https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html