TotalComms is a telecommunications company formed from the merging of other 2 telecommunication companies. The business operating model has been unified, the TOGAF 9 Architecture Board approved the…
The correct answer is B. The Migration planning will be conducted as a series of steps: confirming and then coordinating. See the full explanation below for the reasoning.
Question
TotalComms is a telecommunications company formed from the merging of other 2 telecommunication companies. The business operating model has been unified, the TOGAF 9 Architecture Board approved the outline Implementation and Migration Plan the detailed migration planning must know be approved. Your help is needed to work on the migration planning with all the key stakeholders to achieve an agreement. Refer to the scenario above You are the Lead Architect asked to describe accordingly to TOGAF 9 the best way to address the following activities:
- The way the migration planning is conducted.
- What is going to be implemented.
- The stakeholders involved in the implementation.
- The definition of the deliverables to use
Choose one of the following answers
Options
- AThe Chief Architect will conduct the Migration planning and then share it with the other domain
- BThe Migration planning will be conducted as a series of steps: confirming and then coordinating
- CImplementation and Migration Strategy will be used to define project plans focusing on scope,
- DThis step will be conducted by the Enterprise Architecture team involving Business, Application,
How the community answered
(24 responses)- A17% (4)
- B71% (17)
- C8% (2)