Which of the following terms is defined as the key interests that are crucially important to the stakeholders in a system?
The correct answer is B. Concerns. In TOGAF and the ISO/IEC 42010 architecture description standard, 'Concerns' are defined as the key interests that are crucially important to stakeholders in a system - such as performance, security, reliability, or cost. 'Viewpoints' are templates for constructing views…
Question
Which of the following terms is defined as the key interests that are crucially important to the stakeholders in a system?
Options
- AViewpoints
- BConcerns
- CRequirements
- DPrinciples
- EViews
How the community answered
(51 responses)- A2% (1)
- B94% (48)
- D4% (2)
Explanation
In TOGAF and the ISO/IEC 42010 architecture description standard, 'Concerns' are defined as the key interests that are crucially important to stakeholders in a system - such as performance, security, reliability, or cost. 'Viewpoints' are templates for constructing views. 'Views' are representations of the system from a particular viewpoint. 'Requirements' are specific needs to be satisfied. 'Principles' are general guidelines that guide decision-making.