nerdexam
Fortinet

NSE5_FSM-6.3 · Question #6

Which is a requirement for implementing FortiSIEM disaster recovery?

The correct answer is D. DNS names must be used for the worker upload addresses. DNS Names are used for the Supervisor nodes at the two sites. Make sure that users, collectors, and agents can access both Supervisor nodes by their DNS names. DNS Names are used for the Worker upload addresses…

Integration with Fortinet Security Fabric

Question

Which is a requirement for implementing FortiSIEM disaster recovery?

Options

  • AAll worker nodes must access both supervisor nodes using IP.
  • BSNMP, and WMI ports must be open between the two supervisor nodes.
  • CThe two supervisor nodes must have layer 2 connectivity.
  • DDNS names must be used for the worker upload addresses.

How the community answered

(35 responses)
  • A
    11% (4)
  • B
    6% (2)
  • C
    3% (1)
  • D
    80% (28)

Explanation

DNS Names are used for the Supervisor nodes at the two sites. Make sure that users, collectors, and agents can access both Supervisor nodes by their DNS names. DNS Names are used for the Worker upload addresses. https://docs.fortinet.com/document/fortisiem/5.4.0/disaster-recovery-procedures- nfs/565771/disaster-recovery

Topics

#disaster recovery#supervisor nodes#DNS configuration#high availability