Your customer has a healthy SnapMirror SVM replication between ClusterA and ClusterB. During maintenance, they want to serve the data from ClusterB. Which two NetApp ONTAP System Manager steps must…

The correct answer is B. Stop the SVM on ClusterA. C. Start the SVM on ClusterB. To serve data from the SnapMirror SVM destination (ClusterB), ONTAP requires that the source SVM on ClusterA is stopped, to prevent conflicts, and the destination SVM on ClusterB is started, allowing it to take over serving data. These steps must be done manually in System…

Data Protection Solutions Management

Question

Your customer has a healthy SnapMirror SVM replication between ClusterA and ClusterB. During maintenance, they want to serve the data from ClusterB. Which two NetApp ONTAP System Manager steps must be performed before shutting down ClusterA? (Choose two.)

Options

  • AManually resume the relationship.
  • BStop the SVM on ClusterA.
  • CStart the SVM on ClusterB.
  • DManually quiesce the relationship.

How the community answered

(50 responses)
  • A
    10% (5)
  • B
    74% (37)
  • D
    16% (8)

Explanation

To serve data from the SnapMirror SVM destination (ClusterB), ONTAP requires that the source SVM on ClusterA is stopped, to prevent conflicts, and the destination SVM on ClusterB is started, allowing it to take over serving data. These steps must be done manually in System Manager or CLI prior to accessing data from the destination SVM.

Topics

#SnapMirror SVM#maintenance switchover#SVM management#quiesce