Referring to the exhibit. What are two viable scenarios to test LUN multipathing on Host 1? (Choose two.)

The correct answer is A. Reboot one of the switches. C. Disconnect one of the host cables. See the full explanation below for the reasoning.

Question

Referring to the exhibit. What are two viable scenarios to test LUN multipathing on Host 1? (Choose two.)

Exhibit

NS0-520 question #73 exhibit

Options

  • AReboot one of the switches.
  • BDisable one of the FC LIFs on Controller 1.
  • CDisconnect one of the host cables.
  • DReboot Host 1.

How the community answered

(53 responses)
  • A
    72% (38)
  • B
    11% (6)
  • D
    17% (9)