You have completed the baseline copy for a new inter-cluster SnapMirror relationship. How do you verify the baseline without making the destination volume writable? Response:

The correct answer is A. Create Snapshot copy and a FlexClone volume clone of the SnapMirror destination volume. See the full explanation below for the reasoning.

Question

You have completed the baseline copy for a new inter-cluster SnapMirror relationship. How do you verify the baseline without making the destination volume writable? Response:

Options

  • ACreate Snapshot copy and a FlexClone volume clone of the SnapMirror destination volume.
  • BCreate a FlexClone volume clone of the SnapMirror source volume and then verify the clone.
  • CBreak the mirror and verify the destination volume online.
  • DBreak the mirror and verify the source and destination volumes.

How the community answered

(22 responses)
  • A
    77% (17)
  • B
    14% (3)
  • C
    5% (1)
  • D
    5% (1)