NS0-506 · Question #441

During initial site preparation prior to SAN installation and after ordering is complete, which team's plans are critical to confirm before fabric and storage hardware deployment can begin?

The correct answer is B. Facilities: Space-planning, power, cooling, cabling. See the full explanation below for the reasoning.

Question

During initial site preparation prior to SAN installation and after ordering is complete, which team's plans are critical to confirm before fabric and storage hardware deployment can begin?

Options

  • ABackup team: Offsite volume replication scheduling
  • BFacilities: Space-planning, power, cooling, cabling
  • CStorage administration: Final volume layout
  • DVMware administration: VM assignment to ESXi hosts

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    79% (27)
  • C
    3% (1)
  • D
    6% (2)