The snapvault snap sched -x command is used to ____________.
The correct answer is D. schedule incremental backups. See the full explanation below for the reasoning.
Question
The snapvault snap sched -x command is used to ____________.
Options
- Aschedule full backups
- Bcancel scheduled backups
- Cschedule baseline transfer
- Dschedule incremental backups
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C10% (2)
- D81% (17)