Network_Appliance
NS0-506 · Question #384
You are booting a NetApp storage system for the first time. In which order should the various components be powered on?
The correct answer is D. network switches, disk shelves, any tape backup devices, NetApp controller heads. See the full explanation below for the reasoning.
Question
You are booting a NetApp storage system for the first time. In which order should the various components be powered on?
Options
- Aany tape backup devices, disk shelves, network switches, NetApp controller heads
- BNetApp controller heads, disk shelves, any tape backup devices, network switches
- CNetApp controller heads, disk shelves, network switches, any tape backup devices
- Dnetwork switches, disk shelves, any tape backup devices, NetApp controller heads
How the community answered
(63 responses)- A5% (3)
- B3% (2)
- C14% (9)
- D78% (49)
Community Discussion
No community discussion yet for this question.