Question

Click the Exhibit button. cl01::>lun resize -vserver svm1 -volume db1_vol -lun db1 -size 4096g Error: command failed: New size exceeds this LUN's initial geometry cl01::> What is the reason for the error shown in the exhibit?

Options

  • AThe LUN is thin provisioned, but the parent volume is thick provisioned and cannot satisfy the
  • BThe aggregate over commitment threshold has been exceeded.
  • CThe parent volume that contains the LUN is out of space.
  • DThe LUN cannot be grown past its maximum resize size.

Community Discussion