Network_Appliance
NS0-506 · Question #23
NS0-506 Question #23: Real Exam Question with Answer & Explanation
The correct answer is D. The LUN cannot be grown past its maximum resize size.. See the full explanation below for the reasoning.
Question
Click the Exhibit button. cl01::>lun resize -vserver svm1 -volume db1_vol -lun db1 -size 4096g Error: command failed: New size exceeds this LUN's initial geometry cl01::> What is the reason for the error shown in the exhibit?
Options
- AThe LUN is thin provisioned, but the parent volume is thick provisioned and cannot satisfy the
- BThe aggregate over commitment threshold has been exceeded.
- CThe parent volume that contains the LUN is out of space.
- DThe LUN cannot be grown past its maximum resize size.
Community Discussion
No community discussion yet for this question.