When building your implementation plan, providing dual power for all systems is critical. Which three actions should be mandated? (Choose three.)

The correct answer is A. Dual power supplies should be placed in all equipment. B. Dual power feeds should be run to all equipment. E. Power feeds should be connected to separate outlets connected to two separate PDUs. See the full explanation below for the reasoning.

Question

When building your implementation plan, providing dual power for all systems is critical. Which three actions should be mandated? (Choose three.)

Options

  • ADual power supplies should be placed in all equipment.
  • BDual power feeds should be run to all equipment.
  • CPower feeds should be connected to the closest available outlet inside the cabinet.
  • DPower feeds should be connected to separate circuits on the same data center PDU.
  • EPower feeds should be connected to separate outlets connected to two separate PDUs.

How the community answered

(43 responses)
  • A
    72% (31)
  • C
    9% (4)
  • D
    19% (8)