What is the appropriate method for testing high availability controller failover?

The correct answer is C. issue the takeover command from a controller. See the full explanation below for the reasoning.

Question

What is the appropriate method for testing high availability controller failover?

Options

  • Apull a power cord from a power supply on a controller
  • Bshut down a controller
  • Cissue the takeover command from a controller
  • Dissue the giveback command from a controller

How the community answered

(18 responses)
  • A
    17% (3)
  • B
    6% (1)
  • C
    72% (13)
  • D
    6% (1)