Without adding new cluster interconnect switches, you want to nondisruptively upgrade from FAS2554 controllers to FAS8200 controllers on an existing 2-node switchless cluster running ONTAP 9.5…

The correct answer is A. Relocate the aggregates to one FAS2554 node, takeover, replace the node in takeover state with. Vendor: Network Appliance Exam Code: NS0 Exam Name: NetApp Certified Storage Installation Engineer, ONTAP , LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email…

Install NetApp ONTAP Hardware

Question

Without adding new cluster interconnect switches, you want to nondisruptively upgrade from FAS2554 controllers to FAS8200 controllers on an existing 2-node switchless cluster running ONTAP 9.5 software. Which statement is correct in this scenario?

Options

  • ARelocate the aggregates to one FAS2554 node, takeover, replace the node in takeover state with
  • BConnect the FAS8200 to the FAS2554 with interconnect cables, join the existing cluster, relocate
  • CSet up the FAS8200 as a new cluster, move the SVMs from the FAS2554 to the FAS8200 using
  • DYou cannot perform this task nondisruptively.

How the community answered

(35 responses)
  • A
    71% (25)
  • B
    14% (5)
  • C
    9% (3)
  • D
    6% (2)

Explanation

Vendor: Network Appliance Exam Code: NS0 Exam Name: NetApp Certified Storage Installation Engineer, ONTAP , LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.