The full boot cycle of the CN1610 should take approximately 50 seconds. What should you do to minimize the interruption?
The correct answer is C. You can migrate Data LIFs to different ports on different nodes. See the full explanation below for the reasoning.
Question
The full boot cycle of the CN1610 should take approximately 50 seconds. What should you do to minimize the interruption?
Options
- ARemove all of the cables from the CN1610 CL1 switch, and then connect them to different ports
- BYou can migrate the cluster LIFs from the switch that is to be rebooted, and then revert the cluster
- CYou can migrate Data LIFs to different ports on different nodes.
- DOn each respective switch, use the network interface migrate command to migrate the inter-
How the community answered
(38 responses)- A5% (2)
- B16% (6)
- C71% (27)
- D8% (3)