A customer has a MetroCluster in which one site had suffered a power outage. The MetroCluster performed a switchover to the secondary site. The storage administrator is now preparing to run a DR…

The correct answer is B. metrocluster heal root-aggregates C. metrocluster heal aggregates. You've hit your limit · resets 5am (America/New_York)

Operating and Managing MetroCluster Solutions

Question

A customer has a MetroCluster in which one site had suffered a power outage. The MetroCluster performed a switchover to the secondary site. The storage administrator is now preparing to run a DR switchback, to restore normal operations across the two sites for the MetroCluster. Which two commands does the administrator have to run before the switchback? (Choose two).

Options

  • Astorage aggregate mirror
  • Bmetrocluster heal root-aggregates
  • Cmetrocluster heal aggregates
  • Dsnapmirror resync

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    81% (39)
  • D
    13% (6)

Explanation

You've hit your limit · resets 5am (America/New_York)