Which of the following are critical factors in planning a MetroCluster deployment? (Select two)

The correct answer is A. WAN bandwidth C. Network latency between sites. You've hit your limit · resets 5am (America/New_York)

MetroCluster Planning and Design Considerations

Question

Which of the following are critical factors in planning a MetroCluster deployment? (Select two)

Options

  • AWAN bandwidth
  • BRack size
  • CNetwork latency between sites
  • DOffice furniture layout

How the community answered

(42 responses)
  • A
    86% (36)
  • B
    10% (4)
  • D
    5% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#WAN bandwidth#network latency#site planning#deployment requirements