A prospect is seeking a Nutanix solution for a mission critical application that needs to sustain two simultaneous node outages and prefers that the cluster be able to fully rebuild both data and…

The correct answer is C. 6. See the full explanation below for the reasoning.

Question

A prospect is seeking a Nutanix solution for a mission critical application that needs to sustain two simultaneous node outages and prefers that the cluster be able to fully rebuild both data and metadata in the event hardware issues. what is the minimum number of nodes required for the cluster?

Options

  • A4
  • B5
  • C6
  • D7

How the community answered

(59 responses)
  • A
    14% (8)
  • B
    7% (4)
  • C
    76% (45)
  • D
    3% (2)