Question
ABC Corp currently has 50 VMs currently running in production and is interested in sizing a DR cluster. The RTO is 4 hours and the RPO is 2 hours . Each VM has 100GB of data, with a 5% daily change rate .for retention the customer wants to keep 2 weeks of snaps on the DR cluster. What is the minimum amount of storage capacity for the remote cluster to meet the customer's data retention?
Options
- A6TB to 7TB
- B8TB to 9TB
- C10TB to 11TB
- D14TB to 15T
How the community answered
(59 responses)- A8% (5)
- B73% (43)
- C14% (8)
- D5% (3)