A prospect is conducting a Nutanix POC process that will measure the time to revocer from a power loss, the impact of running multiple workloads on the same cluster, and peak storage performance…
The correct answer is B. Use X-Ray with the included scenarios and deliver the X-Ray PDF report. See the full explanation below for the reasoning.
Question
A prospect is conducting a Nutanix POC process that will measure the time to revocer from a power loss, the impact of running multiple workloads on the same cluster, and peak storage performance. The POC results will be presented to the CIO. How can this be achieved with the least room for error?
Options
- AUse X-Ray to generate a single workload and VDbench for the secondary workload.
- BUse X-Ray with the included scenarios and deliver the X-Ray PDF report.
- CUse iOmeter and manually power off the nodes.
- DUse HCI Bench, manually power off the nodes during testing, and export Prism Analysis data.
How the community answered
(39 responses)- A5% (2)
- B82% (32)
- C10% (4)
- D3% (1)
Community Discussion