nerdexam
Nutanix

NCSE-CORE · Question #126

A prospect has 8500GB of capacity provisioned for a non-production VMware cluster. As Part of migrating to Nutanix. the prospect agrees to convert any thick provisioned disks to thin provisioned disks

The correct answer is A. 3.0TiB. See the full explanation below for the reasoning.

Question

A prospect has 8500GB of capacity provisioned for a non-production VMware cluster. As Part of migrating to Nutanix. the prospect agrees to convert any thick provisioned disks to thin provisioned disks. Based on additional data. the total active working set for the cluster has been datermined to be 1TB. When entering the Raw input workload into Sizer, what is the minimum amount of HDD Capacity required for the workload?

Options

  • A3.0TiB
  • B3.5TiB
  • C4.0TiB
  • D7.5TIB

How the community answered

(42 responses)
  • A
    81% (34)
  • B
    12% (5)
  • C
    2% (1)
  • D
    5% (2)

Community Discussion

No community discussion yet for this question.

Full NCSE-CORE Practice