nerdexam
Nutanix

NCSE-CORE · Question #111

When Discussing node failures, a customer raises the concern that if a node that host 100TB of data goes offline, which building data must take an extended period of time?

The correct answer is D. Distribution of rebuild tasks across all nodes. See the full explanation below for the reasoning.

Question

When Discussing node failures, a customer raises the concern that if a node that host 100TB of data goes offline, which building data must take an extended period of time?

Options

  • AUse of redundant hypervisor boot-drives
  • BSupport for all-flash or NVMe platforms
  • CLeveraging a replication-factor of 3
  • DDistribution of rebuild tasks across all nodes

How the community answered

(50 responses)
  • A
    10% (5)
  • B
    4% (2)
  • C
    16% (8)
  • D
    70% (35)

Community Discussion

No community discussion yet for this question.

Full NCSE-CORE Practice