nerdexam
Nutanix

NCP-EUC · Question #11

The operations team have been tasked with increasing overall datacenter efficiency with a target minimum of 80% CPU, memory, and storage capacity utilization. They are requesting usage data from all…

The correct answer is B. Schedule a monthly email report with CPU, Memory, and Storage Usage data across all clusters. The operations team needs data delivered automatically on a monthly cadence to feed into their capacity management software. Prism Central supports scheduling automated email reports that can include CPU, memory, and storage utilization metrics aggregated across all managed…

Manage and Optimize EUC Environments

Question

The operations team have been tasked with increasing overall datacenter efficiency with a target minimum of 80% CPU, memory, and storage capacity utilization. They are requesting usage data from all application owners be sent on a monthly basis to be ingested into their capacity management software. An administrator has an implementation of four Nutanix clusters under the management of a single Prism Central Instance. How should the administrator best provide the data needed to the operations team to ensure adherence to the datacenter utilization directive?

Options

  • AExport the CPU Memory end Storage Usage metrics under Virtual Infrastructure/VMs in Prism
  • BSchedule a monthly email report with CPU, Memory, and Storage Usage data across all clusters
  • CCreate a Metric Chart in Prism Central with CPU, Memory, and Storage usage across all clusters
  • DReview the VM Efficiencies widget in Prism Central and export the data to a comma delimited file

How the community answered

(25 responses)
  • B
    88% (22)
  • C
    8% (2)
  • D
    4% (1)

Explanation

The operations team needs data delivered automatically on a monthly cadence to feed into their capacity management software. Prism Central supports scheduling automated email reports that can include CPU, memory, and storage utilization metrics aggregated across all managed clusters. This approach ensures consistent, repeatable delivery without requiring the administrator to manually export data each month, reducing risk of missed reporting and human error. Option A is a one-time manual export. Option C creates a chart for viewing in the UI but does not deliver data externally. Option D (VM Efficiencies widget) focuses on VM rightsizing, not aggregate cluster utilization. Scheduling a monthly email report (Answer B) directly satisfies the automation and delivery requirements.

Topics

#Capacity Management#Reporting#Prism Central#Resource Utilization

Community Discussion

No community discussion yet for this question.

Full NCP-EUC Practice