Question
An administrator needs to replace an aging SAN and move to a hyper-converged infrastructure. The existing environment consists of the following hosts that are connected to the SAN: - 5xAIX hosts - 3x Hyper-V hosts - 9xESXi hosts - 2x physical SQL Clusters (Windows Server 2012R2 hosts) After deploying a Nutanix AHV cluster, which two actions should the administrator take to meet the requirements? (Choose two.)
Options
- ADeploy Volumes to support the AIX and SQL workloads.
- BMigrate the ESXI workloads to AHV using Move.
- CDeploy Files to support the AIX hosts.
- DMigrate the ESXi and Hyper-V workloads using Move.