Nutanix
NCM-MCI-5.20 · Question #28
A customer needs a DR solution designed around the following requirements: - There are 8 ms of latency between Sites A and B - The administrator needs the shortest RPO/RTO possible - Application…
The correct answer is A. Async. https://portal.nutanix.com/page/documents/details?targetId=Prism-Element-Data-Protection- Guide-v6_0:wc-cluster-dr-nearsync-limitations-r.html
Network operations
Question
A customer needs a DR solution designed around the following requirements:
- There are 8 ms of latency between Sites A and B
- The administrator needs the shortest RPO/RTO possible
- Application consistent snapshots are required
- Use of Nutanix VSS
Which Data Protection Method should be used?
Options
- AAsync
- BMetro Availability
- CNear Sync
- DCloud Connect
How the community answered
(22 responses)- A73% (16)
- B5% (1)
- C18% (4)
- D5% (1)
Explanation
https://portal.nutanix.com/page/documents/details?targetId=Prism-Element-Data-Protection- Guide-v6_0:wc-cluster-dr-nearsync-limitations-r.html
Topics
#disaster recovery#RPO/RTO#async replication#VSS snapshots
Community Discussion