A network architect is implementing an off-premises computing facility and needs to ensure that operations will not be impacted by major outages. Which of the following should the architect consider?
The correct answer is A. Hot site. A hot site is a fully operational backup facility with hardware, network, and data synchronization already in place. It allows for immediate failover in the event of a disaster, minimizing downtime.
Submitted by viktor_hu· Mar 6, 2026Network Operations
Question
A network architect is implementing an off-premises computing facility and needs to ensure that operations will not be impacted by major outages. Which of the following should the architect consider?
Options
- AHot site
- BDCI
- CDirect Connect
- DActive-passive approach
How the community answered
(56 responses)- A93% (52)
- B4% (2)
- C2% (1)
- D2% (1)
Explanation
A hot site is a fully operational backup facility with hardware, network, and data synchronization already in place. It allows for immediate failover in the event of a disaster, minimizing downtime.