A technician needs to install additional access points for a new high speed connection being added in the new office space. Which of the following will MOST likely be installed to allow additional…

The correct answer is C. 110 Block. See the full explanation below for the reasoning.

Question

A technician needs to install additional access points for a new high speed connection being added in the new office space. Which of the following will MOST likely be installed to allow additional CAT5 cable connections?

Options

  • ASmart Jack
  • BDemarc
  • C110 Block
  • D66 Block

How the community answered

(31 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    77% (24)
  • D
    6% (2)