MB6-896 · Question #58

You are planning a project which will receive offers from several vendors. You need to ensure that you receive all competing offers. What should you create?

The correct answer is D. a request for quotation. See the full explanation below for the reasoning.

Question

You are planning a project which will receive offers from several vendors. You need to ensure that you receive all competing offers. What should you create?

Options

  • Aan item requirement
  • Ba purchase requisition
  • Ca purchase order
  • Da request for quotation

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    15% (8)
  • C
    8% (4)
  • D
    74% (39)