Microsoft
MB6-895 · Question #9
MB6-895 Question #9: Real Exam Question with Answer & Explanation
The correct answer is B. the transactions to be included and excluded in the budget funds available D. the main accounts and financial dimensions to be validated E. the worldflow that is required when a budget is exceeded. See the full explanation below for the reasoning.
Question
You are implementing the budget control feature for Contoso, LTD You need to configure the system based on the requirements you have gathered. Which three settings can be defined for the Budget control configuration feature? Each correct answer presents a complete solution.
Options
- Athe various transactions that will have a budget check performed
- Bthe transactions to be included and excluded in the budget funds available
- Cthe budget planning stages and templates for uploading the budget
- Dthe main accounts and financial dimensions to be validated
- Ethe worldflow that is required when a budget is exceeded
Community Discussion
No community discussion yet for this question.