Microsoft
MB6-895 · Question #69
You want to reserve budget funds for planned expenditures. The funds have been requested but not yet approved from a purchase order. You need to set up a budget code for these types of scenarios…
The correct answer is D. pre-encumbrance. https://technet.microsoft.com/en-us/library/hh209638.aspx
Configure and use Budgeting and Cash and Bank Management
Question
You want to reserve budget funds for planned expenditures. The funds have been requested but not yet approved from a purchase order. You need to set up a budget code for these types of scenarios. Which budget type should you assign to the budget code to accomplish this goal?
Options
- Atransfer
- Bencumbrance
- Coriginal budget
- Dpre-encumbrance
How the community answered
(35 responses)- A6% (2)
- B14% (5)
- C3% (1)
- D77% (27)
Explanation
Topics
#pre-encumbrance#budget code#budget type#purchase requisition funds
Community Discussion