You want to reserve budget funds for planned expenditures. The funds have been requested but not yet approved from a purchase order. You need to set up a budget code for these types of scenarios…

The correct answer is D. pre-encumbrance. https://technet.microsoft.com/en-us/library/hh209638.aspx

Configure and use Budgeting and Cash and Bank Management

Question

You want to reserve budget funds for planned expenditures. The funds have been requested but not yet approved from a purchase order. You need to set up a budget code for these types of scenarios. Which budget type should you assign to the budget code to accomplish this goal?

Options

  • Atransfer
  • Bencumbrance
  • Coriginal budget
  • Dpre-encumbrance

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    14% (5)
  • C
    3% (1)
  • D
    77% (27)

Explanation

https://technet.microsoft.com/en-us/library/hh209638.aspx