A budget manager is considering which components of Microsoft Dynamics AX Financials budgeting are required to meet company needs. The key requirement is that department-level budgetary changes for…
The correct answer is C. Budget Control D. Basic Budgeting E. Budget Reservations. See the full explanation below for the reasoning.
Question
A budget manager is considering which components of Microsoft Dynamics AX Financials budgeting are required to meet company needs. The key requirement is that department-level budgetary changes for the following year must undergo an approval process through the requester's manager and a final approval by the budget manager. Which three Dynamics AX budgeting components are required to accomplish budget tracking and workflow for the following year's budget? Each correct answer presents part of the solution.
Options
- ABudget Register Entries
- BBudget Planning
- CBudget Control
- DBasic Budgeting
- EBudget Reservations
How the community answered
(45 responses)- A7% (3)
- B9% (4)
- C84% (38)
Community Discussion