Question
Your company is planning on using budget control. You need to designate which document types will have budget control on line-entry and which document types will have budget control upon posting. Which three documents allow you to enable the budget control at line-entry? Each correct answer presents a complete solution.
Options
- APurchase Requisitions
- BSales Orders
- CProject Timesheets
- DExpense Reports
- EPurchase Orders
How the community answered
(18 responses)- A72% (13)
- B6% (1)
- C22% (4)