Question
A standard cost variance has affected the general ledger accounts assigned to the lot size variance type of a specific batch order. What is the cause of a lot size variance?
Options
- Adifferent batch quantity or constant costs
- Bdifferent costs reported
- Cchanges to production bill of materials (BOM) or route
- Ddifferent quantity consumed