You need to set up consolidated batch orders to link a bulk order to packed orders. Which of the following actions is part of the setup process?
The correct answer is B. Define the bulk item conversion for formula items. See the full explanation below for the reasoning.
Question
You need to set up consolidated batch orders to link a bulk order to packed orders. Which of the following actions is part of the setup process?
Options
- ADefine the bulk item conversion for by-product items.
- BDefine the bulk item conversion for formula items.
- CDefine the bulk item conversion for planning item items.
- DDefine the bulk item conversion for BOM items.
How the community answered
(23 responses)- A4% (1)
- B83% (19)
- C9% (2)
- D4% (1)