Microsoft
MB6-886 · Question #2
The formula for a finished good named FG-01 uses a raw material named RM-01. You currently have a supply of RM-01 in stock. The vendor informs you that only limited supplies of RM-01 will be…
The correct answer is B. Plan group and Priority. See the full explanation below for the reasoning.
Question
The formula for a finished good named FG-01 uses a raw material named RM-01. You currently have a supply of RM-01 in stock. The vendor informs you that only limited supplies of RM-01 will be available in the future. After you run out of the current supply of RM-01you will substitute a raw material named RM-02 in the FG-01 formula. Which of the following options must you configure on a formula line to allow raw material substitutions in Microsoft Dynamics AX 2012?
Options
- APercent and Priority
- BPlan group and Priority
- CScalable and Percent controlled
- DStep consumption
How the community answered
(46 responses)- A4% (2)
- B85% (39)
- C2% (1)
- D9% (4)
Community Discussion