In Microsoft Dynamics AX 2012, on which calendar is the date dimension of the default cubes based?

The correct answer is C. Gregorian. See the full explanation below for the reasoning.

Question

In Microsoft Dynamics AX 2012, on which calendar is the date dimension of the default cubes based?

Options

  • A360 day
  • Bfiscal year
  • CGregorian
  • DISO week date

How the community answered

(65 responses)
  • A
    5% (3)
  • B
    11% (7)
  • C
    82% (53)
  • D
    3% (2)