You create a new product change case for a bill of materials (BOM). You need to identify which actions are available for the entity associated to the new case. Which three actions should you…

The correct answer is A. Print C. Expire D. Approve. Approvals and validations are available for product change cases, so that you can manage the release of changed BOMs, formulas, and routes to planning and production processes. - You can approve, activate, and expire the entities that are associated with a case

Set up and Configure Inventory Management

Question

You create a new product change case for a bill of materials (BOM). You need to identify which actions are available for the entity associated to the new case. Which three actions should you identify? Each correct answer presents a complete solution.

Options

  • APrint
  • BActivate
  • CExpire
  • DApprove
  • ECalculate

How the community answered

(49 responses)
  • A
    69% (34)
  • B
    12% (6)
  • E
    18% (9)

Explanation

  • Approvals and validations are available for product change cases, so that you can manage the release of changed BOMs, formulas, and routes to planning and production processes. - You can approve, activate, and expire the entities that are associated with a case