You are defining product masters for your organization. You create multiple items before realizing that you failed to assign a size and color variant group to the items. At which stage of the…
The correct answer is D. When the product has not been released to any companies. See the full explanation below for the reasoning.
Question
You are defining product masters for your organization. You create multiple items before realizing that you failed to assign a size and color variant group to the items. At which stage of the product release cycle should you add the variant groups to the items?
Options
- AWhen the product has been released to all companies but has not been used
- BWhen the product has been released to only one company and has not been used
- CWhen the product has been released to only one company and has been used on a sale only
- DWhen the product has not been released to any companies
How the community answered
(59 responses)- A15% (9)
- B3% (2)
- C7% (4)
- D75% (44)