Question
You work as a software developer at XYZ.com. The company runs Microsoft Dynamics CRM 2011 for its customer relationship management software. The Microsoft Dynamics CRM event processing subsystem executes plug-ins based on a message pipeline execution model. No custom plug-ins can be registered during which of the following event pipeline stages
Options
- APre-validation, stage number 10.
- BPre-operation, stage number 20.
- CMainOperation, stage number 30.
- DPost-operation, stage number 40.
- EPost-operation (Deprecated), stage number 50.