Microsoft
MB2-876 · Question #102
You work as a project manager at XYZ.com. The company runs Microsoft Dynamics CRM 2011 for its customer relationship management software. You have created some records for a new project in an entity…
The correct answer is B. You should configure the Reparent privilege. See the full explanation below for the reasoning.
Question
You work as a project manager at XYZ.com. The company runs Microsoft Dynamics CRM 2011 for its customer relationship management software. You have created some records for a new project in an entity in Microsoft Dynamics CRM 2011. You are the owner of the records. You need to configure privileges to assign a different parent to the records. Which of the following entity-based privileges should you configure?
Options
- AYou should configure the Share privilege.
- BYou should configure the Reparent privilege.
- CYou should configure the Assign privilege.
- DYou should configure the Read privilege.
- EYou should configure the Write privilege.
How the community answered
(47 responses)- A2% (1)
- B85% (40)
- C2% (1)
- D4% (2)
- E6% (3)
Community Discussion