After months of planning and testing an MDM solution has been rolled out to a multinational organization. Which of the following should occur NEXT to ensure administration and upkeep of this…
The correct answer is A. Post-implementation feedback. See the full explanation below for the reasoning.
Question
After months of planning and testing an MDM solution has been rolled out to a multinational organization. Which of the following should occur NEXT to ensure administration and upkeep of this solution in the future?
Options
- APost-implementation feedback
- BSoftware development lifecycle management
- CPost-pilot lessons learned
- DEnd-user license agreement roll-out
How the community answered
(28 responses)- A79% (22)
- B4% (1)
- C11% (3)
- D7% (2)