The correct answer is C. costing type to planned and block activation to no. See the full explanation below for the reasoning.
Question
A manufacturing company produces finished goods that contain raw materials that are costed using first-in. You need to set up a costing version to support planned costs of the finished goods. What should you configure in the costing version? Select only one answer.
Options
- Acosting type to standard and block activation to yes
- Bcosting type to planned and block activation to yes
- Ccosting type to planned and block activation to no
- Dcosting type to standard and block activation to no