A customer produces light projection toys for holiday decorations throughout the year. The production process creates the projections toy at the following work cells stands, main assembly, electric…
The correct answer is C. Set the transfer activity Freighted by value to Recipient. https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/activity-based-subcontracting#subcontracted-transfer-activities
Configure Dynamics 365 Supply Chain Management, Manufacturing
Question
A customer produces light projection toys for holiday decorations throughout the year. The production process creates the projections toy at the following work cells stands, main assembly, electric, visuals, and packaging. Vendors must create visual templates for the company for each season. They must manage the transfer of visual templates to the warehouse. Each transfer for each vendor must use the same purchase agreement. You need to configure the subcontracted transfer activity. What should you do?
Options
- ASet the transfer activity Freighted by value to Carrier.
- BSet the transfer activity Freighted by value to Shipper.
- CSet the transfer activity Freighted by value to Recipient.
- DSet the transfer activity Freighted by value to Carrier.
- ESet the transfer activity Freighted by value to Shipper.
- FSet the transfer activity Freighted by value to Recipient.
How the community answered
(51 responses)- A10% (5)
- B6% (3)
- C80% (41)
- E2% (1)
- F2% (1)
Explanation
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/activity-based-subcontracting#subcontracted-transfer-activities