Question
You are the production scheduler at a manufacturing company. The company is not using advanced warehousing. You have firmed a planned production order from master planning. The order is ready to be processed. You now need to process the order in production control. What should you do first?
Options
- AReport the order as finished
- BEstimate the order
- CSchedule the order
- DStart the order
How the community answered
(20 responses)- A15% (3)
- B70% (14)
- C5% (1)
- D10% (2)