A company implements Dynamics 365 Supply Chain Management. Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company…
The correct answer is A. Modify the overflow work activity and assign it to subcontractor B. Create transfer activities and assign them to the subcontractor C. Create a resource and work cell resource group for the subcontractor. https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/manage- subcontract-work-production
Configure third-party connections
Question
A company implements Dynamics 365 Supply Chain Management. Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements: - Locate a warehouse at the subcontractor building. - Support picking and shipping activity tracking. - Associate costs of transporting materials between the locations in the cost of the finished product. You need to modify the production flow. Which three actions should you perform?Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
Options
- AModify the overflow work activity and assign it to subcontractor
- BCreate transfer activities and assign them to the subcontractor
- CCreate a resource and work cell resource group for the subcontractor
- DCreate a new production flow version
- EModify the overflow work operation and associate it with the subcontractor
How the community answered
(21 responses)- A86% (18)
- D10% (2)
- E5% (1)
Explanation
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/manage- subcontract-work-production