You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: The setup uses a Lean schedule group with a throughput…
The correct answer is B. Create a route with a runtime = 1, a process quantity = 10. https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-
Configure Dynamics 365 Supply Chain Management, Manufacturing
Question
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: The setup uses a Lean schedule group with a throughput ratio = 2. The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1. The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day). The throughput is 10 per hour. You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?
Options
- ACreate a route with a runtime = 1, a process quantity = 6,
- BCreate a route with a runtime = 1, a process quantity = 10,
- CCreate a route with a runtime = 1, a process quantity = 6,
- DCreate a route with a runtime = 1, a process quantity = 1,
How the community answered
(59 responses)- A3% (2)
- B75% (44)
- C14% (8)
- D8% (5)
Explanation
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-