You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: The setup uses a Lean schedule group with a throughput…

The correct answer is B. Create a route with a runtime = 1, a process quantity = 10. https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-

Configure Dynamics 365 Supply Chain Management, Manufacturing

Question

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: The setup uses a Lean schedule group with a throughput ratio = 2. The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1. The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day). The throughput is 10 per hour. You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?

Options

  • ACreate a route with a runtime = 1, a process quantity = 6,
  • BCreate a route with a runtime = 1, a process quantity = 10,
  • CCreate a route with a runtime = 1, a process quantity = 6,
  • DCreate a route with a runtime = 1, a process quantity = 1,

How the community answered

(59 responses)
  • A
    3% (2)
  • B
    75% (44)
  • C
    14% (8)
  • D
    8% (5)

Explanation

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-

Topics

#lean to discrete conversion#throughput ratio#route configuration#Kanban capacity