MB-310 · Question #112
You are a Dynamics 365 Finance consultant. You plan to configure the allocation base, cost behavior, and cost distribution. Which three actions do these configurations accomplish? Each correct…
The correct answer is A. Spread costs from one cost object to one or more other cost objects by applying a relevant B. Measure and quantify activities, such as machine hours that are used, kilowatt hours that are E. Classify costs according to their behavior in relation to changes in key business activities. Cost distribution: used to distribute cost from one cost object to one or more other cost objects by applying a relevant allocation base Allocation base: used to measure and quantify activities, such as machine hours that are used, kilowatt hours that are consumed, or square…
Question
Options
- ASpread costs from one cost object to one or more other cost objects by applying a relevant
- BMeasure and quantify activities, such as machine hours that are used, kilowatt hours that are
- CSpread the balance of the cost from one cost object to one or more other cost objects by applying
- DControl which journals can be used in the costing process.
- EClassify costs according to their behavior in relation to changes in key business activities.
How the community answered
(51 responses)- A73% (37)
- C18% (9)
- D10% (5)
Explanation
Cost distribution: used to distribute cost from one cost object to one or more other cost objects by applying a relevant allocation base Allocation base: used to measure and quantify activities, such as machine hours that are used, kilowatt hours that are consumed, or square footage that is occupied. It's used as basis for allocating costs to one or more cost objects Cost behavior: classifies costs according to their behavior in relation to changes in key business https://docs.microsoft.com/en-us/dynamics365/finance/cost-accounting/terms-cost-accounting
Topics
Community Discussion
No community discussion yet for this question.